FTC administrative order · issued 13 January 2025

Gravy Analytics, Inc., In the Matter of

Duties30in this order
Parties bound2as written in the order
Order date202513 January, printed in the order
Last end date204513 January 2045, worked out from the order
Forum
FTC administrative order
Docket
C-4810
Order date
2025-01-13 (printed in the order)
Status in the FTC case catalog
Entered or issued, listed on the case page under 2025-01-14
Length of the order
Until 2045-01-13 (20 years from issuance of the order)
Source
Order text (PDF, ftc.gov) | FTC case page
Source file sha256
6d216094e6f06cbd2ffa0f54d45a3c29c06bdaa6f2f17295253b9512be411d1c
Where the 30 duties stand
  • Due date not public 21
  • In force 8
  • No public record of completion found 1

Most compliance is reported privately and never published. No public record does not mean a duty was not met. What each status means.

Parties bound, as written in the order

  • Gravy Analytics, Inc. Respondent, DE44679 Endicott Dr Suite 300, Ashburn, VA 20147
  • Venntel, Inc. Respondent, DE2201 Cooperative Way, Suite 600, Herndon, Virginia 20171
Fig. 01 – the clock on this order

Every dated duty, on one line each.

20 of 30 duties are drawn. The others have no date that can be worked out from the public record, or no clock at all.

2025202620272028202920302031203220332034203520362037203820392040204120422043204420452046XVI.A: One year after issuance each Respondent submits a sworn compliance report with contact points, business details and a description of compliance. (due 2026-01-13)XVI.AOne year after issuance each…XV.B: For 5 years Respondents deliver a copy of the Order to principals, officers, directors, relevant managers and agents, within 10 days of the effective date for current personnel and before others assume responsibilities. (2025-01-13 to 2030-01-13)XV.BFor 5 years Respondents deliver…XVII: For 5 years after issuance Respondents create, and retain for 5 years, accounting, personnel, complaint, law-enforcement, representation, consent, supplier, sensitive-location and compliance records. (2025-01-13 to 2030-01-13)XVIIFor 5 years after issuance…I: Respondents must not misrepresent how they review data suppliers' consent frameworks, how they handle Covered Information, or whether Location Data is Deidentified. (2025-01-13 to 2045-01-13)IRespondents must not…II: Respondents must not sell, license, transfer, share, disclose or use Sensitive Location Data tied to Sensitive Locations identified under their program, except data converted to non-sensitive form or used with Affirmative Express Consent to provide a service the consumer requested. (2025-01-13 to 2045-01-13)IIRespondents must not sell…III: Within 90 days of the effective date Respondents establish, implement and maintain a Sensitive Location Data Program with a Sensitive Locations list, accountable officer, quarterly assessment and testing, and prompt deletion steps. (2025-01-13 to 2045-01-13)IIIWithin 90 days of the effective…IV: Within 90 days of the effective date Respondents establish and maintain policies, procedures and technical measures, including recipient contract terms, marking and annual recipient assessments, to prevent associating Location Data with certain locations or identifying homes. (2025-01-13 to 2045-01-13)IVWithin 90 days of the effective…IX: Respondents provide a simple, easily-located means for consumers to withdraw consent to use or disclosure of their device's Location Data. (2025-01-13 to 2045-01-13)IXRespondents provide a simple…VI.A: Respondents must not collect, use, maintain or disclose Location Data from devices where the consumer has opted out of targeted advertising or tracking, absent a record documenting consent. (2025-01-13 to 2045-01-13)VI.ARespondents must not collect…VI.B: Within 90 days of the effective date Respondents must not collect, use, maintain or disclose an individual's Location Data without a record documenting the consumer's prior consent. (2025-01-13 to 2045-01-13)VI.BWithin 90 days of the effective…VII: Within 90 days of the effective date Respondents implement and maintain a Supplier Assessment Program to ensure consumer consent for precise location data, with initial and annual supplier assessments and records. (2025-01-13 to 2045-01-13)VIIWithin 90 days of the effective…VIII: Respondents provide a clear and conspicuous means for consumers to request the identity of entities to which their Location Data was disclosed, or alternatively a deletion-request method meeting stated conditions. (2025-01-13 to 2045-01-13)VIIIRespondents provide a clear and…X: Respondents cease using and disclosing all Location Data tied to a device within 15 days after notice that the consumer withdrew consent. (2025-01-13 to 2045-01-13)XRespondents cease using and…XI: Respondents maintain a simple, clear means for consumers to request deletion of their device's Location Data and delete it within 30 days of the request unless a shorter period is required by law. (2025-01-13 to 2045-01-13)XIRespondents maintain a simple…XII.A: Within 60 days of the effective date Respondents document, follow and publicly post a retention schedule for Covered Information, with no indefinite retention. (2025-01-13 to 2045-01-13)XII.AWithin 60 days of the effective…XII.C: Before collecting or using a new type of consumer information, Respondents update their retention schedule with purpose, business need and a deletion timeframe. (2025-01-13 to 2045-01-13)XII.CBefore collecting or using a…XIV: Within 60 days of the effective date Respondents establish, implement and maintain a comprehensive privacy program for Covered Information, with documentation, risk assessments, safeguards, training and annual testing. (2025-01-13 to 2045-01-13)XIVWithin 60 days of the effective…XIX: The Order terminates 20 years from issuance, or 20 years from the most recent federal court complaint alleging a violation of the Order, whichever is later, subject to stated provisos. (2025-01-13 to 2045-01-13)XIXThe Order terminates 20 years…XVI.B: Respondents submit a sworn compliance notice within 14 days of any change in point of contact or in structure that may affect compliance. (2025-01-13 to 2045-01-13)XVI.BRespondents submit a sworn…XVIII.B: Respondents permit Commission representatives to interview anyone affiliated with them who has agreed to an interview; counsel may be present. (2025-01-13 to 2045-01-13)XVIII.BRespondents permit…TODAY

Scroll sideways to see the whole chart ›

  • One-time duty, on its due date
  • Continuing duty, from start to end
  • Today

Duties (30)

IProhibition

I: Prohibition. Respondents must not misrepresent how they review data suppliers' consent frameworks, how they handle Covered Information, or whether Location Data is Deidentified.

must not misrepresent, in any manner, expressly or by implication: A. The extent to which Respondents review data suppliers’ compliance and consent frameworks

Quoted from the order text (PDF), clause I.

Who
Respondents
When
No one-time deadline
How long
Until 2045-01-13 (20 years from issuance of the order)
Status
In force. The order requires this for as long as its stated period runs. This says nothing about whether it is being followed.
In force Until 2045-01-13 Source PDF ↗
IIProhibition

II: Prohibition. Respondents must not sell, license, transfer, share, disclose or use Sensitive Location Data tied to Sensitive Locations identified under their program, except data converted to non-sensitive form or used with Affirmative Express Consent to provide a service the consumer requested.

must not sell, license, transfer, share, disclose, or otherwise use in any products or services Sensitive Location Data associated with the Sensitive Locations

Quoted from the order text (PDF), clause II.

Who
Respondents
When
No one-time deadline
How long
Until 2045-01-13 (20 years from issuance of the order)
Status
In force. The order requires this for as long as its stated period runs. This says nothing about whether it is being followed.
In force Until 2045-01-13 Source PDF ↗
IIIRequired action

III: Required action. Within 90 days of the effective date Respondents establish, implement and maintain a Sensitive Location Data Program with a Sensitive Locations list, accountable officer, quarterly assessment and testing, and prompt deletion steps.

Respondents, within 90 days of the effective date of this Order, must establish and implement, and thereafter maintain, a Sensitive Location Data Program

Quoted from the order text (PDF), clause III.

Who
Respondents
When
Due 90 days after the order's effective date; date not public
How long
Until 2045-01-13 (20 years from issuance of the order)
Status
Due date not public. The order sets a deadline counted from a date or event that is not public, such as an effective date, a date of service or a divestiture, so the due date cannot be worked out and is not shown as passed.
Due date not public Until 2045-01-13 Source PDF ↗
IVRequired action

IV: Required action. Within 90 days of the effective date Respondents establish and maintain policies, procedures and technical measures, including recipient contract terms, marking and annual recipient assessments, to prevent associating Location Data with certain locations or identifying homes.

within 90 days of the effective date of this Order, must establish and implement and thereafter maintain policies, procedures, and technical measures designed to prevent Respondents or recipients of Respondents’ Location Data

Quoted from the order text (PDF), clause IV.

Who
Respondents
When
Due 90 days after the order's effective date; date not public
How long
Until 2045-01-13 (20 years from issuance of the order)
Status
Due date not public. The order sets a deadline counted from a date or event that is not public, such as an effective date, a date of service or a divestiture, so the due date cannot be worked out and is not shown as passed.
Due date not public Until 2045-01-13 Source PDF ↗
VReporting

V: Reporting. Within 30 days of determining that a Third-Party Incident has occurred, Respondents submit a sworn report to the Commission with specified details.

within 30 days of any Respondent’s determination that a Third-Party Incident has occurred, Respondents must submit a report to the Commission.

Quoted from the order text (PDF), clause V.

Who
Respondents (reports to: Commission)
When
Due 30 days, counted from the event “Respondent's determination that a Third-Party Incident has occurred”; date not public
Status
Due date not public. The order sets a deadline counted from a date or event that is not public, such as an effective date, a date of service or a divestiture, so the due date cannot be worked out and is not shown as passed.
Due date not public No fixed date Source PDF ↗
VI.AProhibition

VI.A: Prohibition. Respondents must not collect, use, maintain or disclose Location Data from devices where the consumer has opted out of targeted advertising or tracking, absent a record documenting consent.

must not: A. Collect, use, maintain, or disclose Location Data from devices where a consumer has enabled the mobile operating system privacy settings to opt out of, limit, or otherwise decline targeted advertising or tracking

Quoted from the order text (PDF), clause VI.A.

Who
Respondents
When
No one-time deadline
How long
Until 2045-01-13 (20 years from issuance of the order)
Status
In force. The order requires this for as long as its stated period runs. This says nothing about whether it is being followed.
In force Until 2045-01-13 Source PDF ↗
VI.BProhibition

VI.B: Prohibition. Within 90 days of the effective date Respondents must not collect, use, maintain or disclose an individual's Location Data without a record documenting the consumer's prior consent.

Within 90 days of the effective date of this Order, collect, use, maintain, or disclose an individual's Location Data without a record satisfying the requirements in Provision VII.B

Quoted from the order text (PDF), clause VI.B.

Who
Respondents
When
Due 90 days after the order's effective date; date not public
How long
Until 2045-01-13 (20 years from issuance of the order)
Status
Due date not public. The order sets a deadline counted from a date or event that is not public, such as an effective date, a date of service or a divestiture, so the due date cannot be worked out and is not shown as passed.
Due date not public Until 2045-01-13 Source PDF ↗
VIIRequired action

VII: Required action. Within 90 days of the effective date Respondents implement and maintain a Supplier Assessment Program to ensure consumer consent for precise location data, with initial and annual supplier assessments and records.

Respondents, within 90 days of the effective date of this Order, must implement a program designed to ensure that consumers have provided consent for the collection and use of all data that may reveal a mobile device or consumer’s precise location

Quoted from the order text (PDF), clause VII.

Who
Respondents
When
Due 90 days after the order's effective date; date not public
How long
Until 2045-01-13 (20 years from issuance of the order)
Status
Due date not public. The order sets a deadline counted from a date or event that is not public, such as an effective date, a date of service or a divestiture, so the due date cannot be worked out and is not shown as passed.
Due date not public Until 2045-01-13 Source PDF ↗
VIIIRequired action

VIII: Required action. Respondents provide a clear and conspicuous means for consumers to request the identity of entities to which their Location Data was disclosed, or alternatively a deletion-request method meeting stated conditions.

Conspicuous means for consumers to request the identity of any entity, business, or individual as to which Respondents have knowledge that consumers’ Location Data was sold, transferred, licensed, or otherwise disclosed.

Quoted from the order text (PDF), clause VIII.

Who
Respondents
When
No one-time deadline
How long
Until 2045-01-13 (20 years from issuance of the order)
Status
In force. The order requires this for as long as its stated period runs. This says nothing about whether it is being followed.
In force Until 2045-01-13 Source PDF ↗
IXRequired action

IX: Required action. Respondents provide a simple, easily-located means for consumers to withdraw consent to use or disclosure of their device's Location Data.

located means for consumers to withdraw consent to Respondents’ use or disclosure of their device’s Location Data.

Quoted from the order text (PDF), clause IX.

Who
Respondents
When
No one-time deadline
How long
Until 2045-01-13 (20 years from issuance of the order)
Status
In force. The order requires this for as long as its stated period runs. This says nothing about whether it is being followed.
In force Until 2045-01-13 Source PDF ↗
XRequired action

X: Required action. Respondents cease using and disclosing all Location Data tied to a device within 15 days after notice that the consumer withdrew consent.

must cease using and disclosing all Location Data associated with a specific device within 15 days after Respondents receive notice that the consumer has withdrawn their consent

Quoted from the order text (PDF), clause X.

Who
Respondents
When
Due 15 days, counted from the event “Respondents receive notice that the consumer has withdrawn consent”; date not public
How long
Until 2045-01-13 (20 years from issuance of the order)
Status
Due date not public. The order sets a deadline counted from a date or event that is not public, such as an effective date, a date of service or a divestiture, so the due date cannot be worked out and is not shown as passed.
Due date not public Until 2045-01-13 Source PDF ↗
XIRequired action

XI: Required action. Respondents maintain a simple, clear means for consumers to request deletion of their device's Location Data and delete it within 30 days of the request unless a shorter period is required by law.

Location Data that Respondents previously collected about their mobile device, and delete such Location Data within 30 days of receipt of such request unless a shorter period for deletion is required by law.

Quoted from the order text (PDF), clause XI.

Who
Respondents
When
Due 30 days, counted from the event “receipt of consumer deletion request”; date not public
How long
Until 2045-01-13 (20 years from issuance of the order)
Status
Due date not public. The order sets a deadline counted from a date or event that is not public, such as an effective date, a date of service or a divestiture, so the due date cannot be worked out and is not shown as passed.
Due date not public Until 2045-01-13 Source PDF ↗
XII.ARequired action

XII.A: Required action. Within 60 days of the effective date Respondents document, follow and publicly post a retention schedule for Covered Information, with no indefinite retention.

Within 60 days of the effective date of this Order, document, adhere to, and make publicly available through a link on the home page of their website(s)

Quoted from the order text (PDF), clause XII.A.

Who
Respondents
When
Due 60 days after the order's effective date; date not public
How long
Until 2045-01-13 (20 years from issuance of the order)
Status
Due date not public. The order sets a deadline counted from a date or event that is not public, such as an effective date, a date of service or a divestiture, so the due date cannot be worked out and is not shown as passed.
Due date not public Until 2045-01-13 Source PDF ↗
XII.BReporting

XII.B: Reporting. Within 60 days of the effective date Respondents give the Commission a written statement describing the published retention schedule.

Within 60 days of the effective date of this Order, Respondents shall provide a written statement to the Commission

Quoted from the order text (PDF), clause XII.B.

Who
Respondents (reports to: Commission)
When
Due 60 days after the order's effective date; date not public
Status
Due date not public. The order sets a deadline counted from a date or event that is not public, such as an effective date, a date of service or a divestiture, so the due date cannot be worked out and is not shown as passed.
Due date not public No fixed date Source PDF ↗
XII.CRequired action

XII.C: Required action. Before collecting or using a new type of consumer information, Respondents update their retention schedule with purpose, business need and a deletion timeframe.

Prior to collecting or using any new type of information related to consumers that was not being collected as of the issuance date of this Order

Quoted from the order text (PDF), clause XII.C.

Who
Respondents
When
Due by the event “collecting or using any new type of information related to consumers”; date not public
How long
Until 2045-01-13 (20 years from issuance of the order)
Status
Due date not public. The order sets a deadline counted from a date or event that is not public, such as an effective date, a date of service or a divestiture, so the due date cannot be worked out and is not shown as passed.
Due date not public Until 2045-01-13 Source PDF ↗
XIII.ARequired action

XIII.A: Required action. Within 60 days of the effective date Respondents delete or destroy all Historic Location Data and confirm in writing to the Commission, unless the proviso applies.

Within 60 days after the effective date of this Order, delete or destroy all Historic Location Data

Quoted from the order text (PDF), clause XIII.A.

Who
Respondents (reports to: Commission)
When
Due 60 days after the order's effective date; date not public
Status
Due date not public. The order sets a deadline counted from a date or event that is not public, such as an effective date, a date of service or a divestiture, so the due date cannot be worked out and is not shown as passed.
Due date not public No fixed date Source PDF ↗
XIII.B(i)Notice

XIII.B(i): Notice. Within 90 days of the effective date Respondents inform customers that received Historic Location Data in the 3 years before issuance of the FTC's deletion requirement.

Within 90 days after the effective date of this Order, (i) inform Respondents’ customers that received Historic Location Data within 3 years prior to the issuance date of this Order

Quoted from the order text (PDF), clause XIII.B(i).

Who
Respondents
When
Due 90 days after the order's effective date; date not public
Status
Due date not public. The order sets a deadline counted from a date or event that is not public, such as an effective date, a date of service or a divestiture, so the due date cannot be worked out and is not shown as passed.
Due date not public No fixed date Source PDF ↗
XIII.B(ii)Reporting

XIII.B(ii): Reporting. Respondents submit copies of the customer notices to the Commission under penalty of perjury within 10 days of sending them.

Respondents shall promptly submit, within 10 days of sending to its customers, all such notices to the Commission under penalty of perjury

Quoted from the order text (PDF), clause XIII.B(ii).

Who
Respondents (reports to: Commission)
When
Due 10 days, counted from the event “sending notices to customers”; date not public
Status
Due date not public. The order sets a deadline counted from a date or event that is not public, such as an effective date, a date of service or a divestiture, so the due date cannot be worked out and is not shown as passed.
Due date not public No fixed date Source PDF ↗
XIII.CRequired action

XIII.C: Required action. Within 90 days of the effective date Respondents delete or destroy all Data Products and confirm in writing to the Commission.

Within 90 days after the effective date of this Order, delete or destroy all Data Products

Quoted from the order text (PDF), clause XIII.C.

Who
Respondents (reports to: Commission)
When
Due 90 days after the order's effective date; date not public
Status
Due date not public. The order sets a deadline counted from a date or event that is not public, such as an effective date, a date of service or a divestiture, so the due date cannot be worked out and is not shown as passed.
Due date not public No fixed date Source PDF ↗
XIVRequired action

XIV: Required action. Within 60 days of the effective date Respondents establish, implement and maintain a comprehensive privacy program for Covered Information, with documentation, risk assessments, safeguards, training and annual testing.

must, within 60 days of the effective date of this Order, establish and implement, and thereafter maintain, a comprehensive privacy program (the “Program”) that protects the privacy of such Covered Information.

Quoted from the order text (PDF), clause XIV.

Who
Respondents
When
Due 60 days after the order's effective date; date not public
How long
Until 2045-01-13 (20 years from issuance of the order)
Status
Due date not public. The order sets a deadline counted from a date or event that is not public, such as an effective date, a date of service or a divestiture, so the due date cannot be worked out and is not shown as passed.
Due date not public Until 2045-01-13 Source PDF ↗
XV.AReporting

XV.A: Reporting. Respondents submit sworn acknowledgments of receipt of the Order to the Commission within 10 days after the effective date.

Respondents, within 10 days after the effective date of this Order, must submit to the Commission acknowledgments of receipt of this Order sworn under penalty of perjury.

Quoted from the order text (PDF), clause XV.A.

Who
Respondents (reports to: Commission)
When
Due 10 days after the order's effective date; date not public
Status
Due date not public. The order sets a deadline counted from a date or event that is not public, such as an effective date, a date of service or a divestiture, so the due date cannot be worked out and is not shown as passed.
Due date not public No fixed date Source PDF ↗
XV.BRequired action

XV.B: Required action. For 5 years Respondents deliver a copy of the Order to principals, officers, directors, relevant managers and agents, within 10 days of the effective date for current personnel and before others assume responsibilities.

For 5 years after the issuance date of this Order, Respondents must deliver a copy of this Order to:

Quoted from the order text (PDF), clause XV.B.

Who
Respondents
When
Due 10 days after the order's effective date; date not public
How long
Until 2030-01-13 (5 years from issuance of the order)
Status
Due date not public. The order sets a deadline counted from a date or event that is not public, such as an effective date, a date of service or a divestiture, so the due date cannot be worked out and is not shown as passed.
Due date not public Until 2030-01-13 Source PDF ↗
XV.CRequired action

XV.C: Required action. Respondents obtain a signed and dated acknowledgment of receipt of the Order from each recipient within 30 days.

Respondents must obtain, within 30 days, a signed and dated acknowledgment of receipt of this Order.

Quoted from the order text (PDF), clause XV.C.

Who
Respondents
When
Due 30 days, counted from the event “delivery of a copy of the Order”; date not public
Status
Due date not public. The order sets a deadline counted from a date or event that is not public, such as an effective date, a date of service or a divestiture, so the due date cannot be worked out and is not shown as passed.
Due date not public No fixed date Source PDF ↗
XVI.AReporting

XVI.A: Reporting. One year after issuance each Respondent submits a sworn compliance report with contact points, business details and a description of compliance.

One year after the issuance date of this Order, each of the Respondents must submit a compliance report, sworn under penalty of perjury

Quoted from the order text (PDF), clause XVI.A.

Who
Respondents (reports to: Commission)
When
Due 2026-01-13 (1 year after issuance of the order)
Status
No public record of completion found. We have not found a public record showing this duty being carried out. Most compliance is reported privately to the agency and never published, so the absence of a public record does not mean the duty was not met.
No public record of completion found Due 2026-01-13 Source PDF ↗
XVI.BNotice

XVI.B: Notice. Respondents submit a sworn compliance notice within 14 days of any change in point of contact or in structure that may affect compliance.

The Respondents must submit a compliance notice, sworn under penalty of perjury, within 14 days of any change in the following

Quoted from the order text (PDF), clause XVI.B.

Who
Respondents (reports to: Commission)
When
Due 14 days, counted from the event “change in designated point of contact or structure of Respondents”; date not public
How long
Until 2045-01-13 (20 years from issuance of the order)
Status
Due date not public. The order sets a deadline counted from a date or event that is not public, such as an effective date, a date of service or a divestiture, so the due date cannot be worked out and is not shown as passed.
Due date not public Until 2045-01-13 Source PDF ↗
XVI.CNotice

XVI.C: Notice. Respondents notify the Commission within 14 days of the filing of any bankruptcy or insolvency proceeding by or against either Respondent.

The Respondents must submit notice of the filing of any bankruptcy petition, insolvency proceeding, or similar proceeding by or against either Respondent within 14 days of its filing.

Quoted from the order text (PDF), clause XVI.C.

Who
Respondents (reports to: Commission)
When
Due 14 days, counted from the event “filing of bankruptcy petition or similar proceeding”; date not public
Status
Due date not public. The order sets a deadline counted from a date or event that is not public, such as an effective date, a date of service or a divestiture, so the due date cannot be worked out and is not shown as passed.
Due date not public No fixed date Source PDF ↗
XVIIRecordkeeping

XVII: Recordkeeping. For 5 years after issuance Respondents create, and retain for 5 years, accounting, personnel, complaint, law-enforcement, representation, consent, supplier, sensitive-location and compliance records.

Respondents must create certain records for 5 years after the issuance date of the Order, and retain each such record for 5 years.

Quoted from the order text (PDF), clause XVII.

Who
Respondents
When
No one-time deadline
How long
Until 2030-01-13 (5 years from issuance of the order)
Status
In force. The order requires this for as long as its stated period runs. This says nothing about whether it is being followed.
In force Until 2030-01-13 Source PDF ↗
XVIII.ACooperation

XVIII.A: Cooperation. Within 14 days of a written request from the Commission Respondents submit sworn compliance reports or information and produce records for inspection and copying.

Within 14 days of receipt of a written request from a representative of the Commission, the Respondents must submit additional compliance reports or other requested information

Quoted from the order text (PDF), clause XVIII.A.

Who
Respondents (reports to: Commission)
When
Due 14 days, counted from the event “receipt of written request from a representative of the Commission”; date not public
Status
Due date not public. The order sets a deadline counted from a date or event that is not public, such as an effective date, a date of service or a divestiture, so the due date cannot be worked out and is not shown as passed.
Due date not public No fixed date Source PDF ↗
XVIII.BCooperation

XVIII.B: Cooperation. Respondents permit Commission representatives to interview anyone affiliated with them who has agreed to an interview; counsel may be present.

Respondents must permit representatives of the Commission to interview anyone affiliated with Respondents who has agreed to such an interview.

Quoted from the order text (PDF), clause XVIII.B.

Who
Respondents (reports to: Commission)
When
No one-time deadline
How long
Until 2045-01-13 (20 years from issuance of the order)
Status
In force. The order requires this for as long as its stated period runs. This says nothing about whether it is being followed.
In force Until 2045-01-13 Source PDF ↗
XIXTerm of the order

XIX: Term of the order. The Order terminates 20 years from issuance, or 20 years from the most recent federal court complaint alleging a violation of the Order, whichever is later, subject to stated provisos.

This Order will terminate 20 years from the date of its issuance (which date may be stated at the end of this Order, near the Commission’s seal), or 20 years from the most recent date that the United States or the Commission files a complaint

Quoted from the order text (PDF), clause XIX.

Who
Respondents
When
No one-time deadline
How long
Until 2045-01-13 (20 years from issuance of the order)
Status
In force. The order requires this for as long as its stated period runs. This says nothing about whether it is being followed.
In force Until 2045-01-13 Source PDF ↗